RV SW cabling has been implemented and tested.
The NE group is working on a plan and timeline to disconnect SE data and phone connectivity to the SW building. The tentative plan is to do the work during the Xmas break this year.
The connections for the fiber to the rack equipment still need to be completed.
Follow up with the NE group on their plan for disconnecting data services from SE from SW.