Thursday, December 9, 2010

Progress Update

There has been very little activity on this project at this time.

Friday, November 19, 2010

Progress Update

The NE group is working on a plan and timeline to disconnect SE data and phone connectivity to the SW building. The tentative plan is to do the work during the Xmas break this year.

Confirm with the NE group on their plan for disconnecting data services from SE from SW.
Clark Construction will be shutting off power to SW from 6 am to 9 am on 11/24 to remove the temporary power that went to the new Science Center.

Thursday, November 4, 2010

Progress Update

The NE group is working on a plan and timeline to disconnect SE data and phone connectivity to the SW building. The tentative plan is to do the work during the Xmas break this year.

Confirm with the NE group on their plan for disconnecting data services from SE from SW.

Friday, October 15, 2010

Progress Update

RV SW cabling has been implemented and tested.
The NE group is working on a plan and timeline to disconnect SE data and phone connectivity to the SW building. The tentative plan is to do the work during the Xmas break this year.
The connections for the fiber to the rack equipment still need to be completed.
Follow up with the NE group on their plan for disconnecting data services from SE from SW.

Friday, October 1, 2010

Progress Update

RV SW cabling has been implemented and tested.
The NE group is working on a plan and timeline to disconnect SE data and phone connectivity to the SW building.
The connections for the fiber to the rack equipment still need to be completed.
Follow up with the NE group on their plan for disconnecting data services from SE from SW.

Wednesday, August 18, 2010

Progress Update

Follow up with vendor and facilities on the start date for running the fiber and copper cable to SW.
Follow up on cabling PO for vendor. Checking with procurement on when and who has received the PO
Meet with project team members to review the room layout for WDCE. They were in agreement that the room size was fine.
The virtualization of the WDCE servers to the existing ITOC in TP is still being worked on with network engineers.

Thursday, August 5, 2010

Progress Update

The cabling vendor is waiting for the material to arrive to start implementing the new pathway for connectivity to the SW building.
The requisition for the infrastructure equipment required for this project has been sent to facilities.

Thursday, June 10, 2010

Progress Update

Setup meeting to have a walkthrough with the vendor and the cabling group to review their scope of work.
Reviewing the cabling quote from the vendor.

Thursday, June 3, 2010

Progress Update

Recieved cabling quote from vendor. A walkthrough needs to be setup with vendor to review there scope of work.

Thursday, May 13, 2010

Progress Update

Continue working with the college cabling group to provide an estimate to run voice, fiber, and Cat6 to the SW building to keep connectivity to the building while SE is being renovated.

Friday, April 30, 2010

Progress Update

Working with the college cabling group to provide an estimate to run voice, fiber, and Cat6 to the SW building to keep connectivity to the building while SE is being renovated.
Follow up on quote estimate from the college cable vendor for re-routing the data lines.

Friday, April 16, 2010

Progress Update

Monitoring projects methodology of power, data and voice to the building.
Continue monitoring any discussions from the RV SE project that impacts the SW project.

Thursday, April 1, 2010

Progress update

Monitoring project on methodology on maintaining data and voice connectivity to the building while RV SE is being renovated.
The new classroom design and teach method is still being discussed with client and facilities.
Communicate with facilities on any decisions with the new classroom design.

Thursday, March 18, 2010

Progress update

I will continue monitoring any project information about the renovation of this building since SE renovation could impact SW project.

The SW project is planned to run a pilot of a new type of classroom design. I will work with the facilities PM on the IT requirements.

Monday, March 8, 2010

Progress Update

The SE meetings have discussed the impact of making sure that SW stays power and connectivity stays active while SE is being renovated.

Wednesday, February 10, 2010

Progress Update

The project continues to be dormant over the past two weeks.

Thursday, January 21, 2010

Progress Update

There was a meeting held on January 11th that discussed the conduit work needed for connectivity to the building. Several options were discussed and will be reviewed by facilities to determine the best and practical solution to bring connectivity to the building.